Construction Updates
|
 |
|
Natatorium
· The kool deck contractor is scheduled to make necessary repairs to the kool deck in November 2011.
· Air structure is scheduled for re-installation the second week of November 2011.
Natatorium Phase II Renovations
· Bids were received on July 11.
· Bass Construction was the low bidder submitted to and accepted by the LCISD board.
· Move out was completed on July 22.
· Pre-construction meeting was held on July 25.
· Abatement scheduled for July 28-31.
· Bass Construction will start work on August 1.
|
|
|
|